Dry Plant Milling & floatation. Structural, mechanical and piping works.
The project comprised of fabrication and erection of over 1000 tons of plate work including tanks, hoppers, chutes and bag splitters.
Installation of mechanical equipments including a primary crusher, pumps and valves.
Others works include piping work comprising of installation of approx 11,000m pipes of varying sizes.