Mechanical, structural and Civil works various work packages. These included:
Project Scope Included works for the new Secondary Crushing plant, Conveyors, process plant, Ball mill and tailings:
Major works executed comprised mainly of;
- Installation of new 11kV switchgear and 11kV cabling including terminations
- Installation of 2 No. 1600kVA 11/0.415kV transformers
- Installation of new M.C.C.’s consisting of approximately 100 starters and control cubicles
- Cable ladder and tray throughout the new plant
- Laying and termination of 11kV, 415V and Instrumentation cabling throughout the plant
- Field instrumentation and control devices throughout the plant
- Fibre optic laying and terminations for SCADA and DCS system
- Installation of switchgear, liquid starters and control equipment for new ball mill
- Earthing, Plant lighting and Small power