Client | PANGEA MINERALS LTD, TANZANIA |
Supervising Engineer | LYCOPODIUM ENGINEERING PTY LTD |
Completion date | JANUARY 2009 |
Project Value | US$ 11.8 Million |
Dry Plant Milling & floatation. Structural, mechanical and piping works.
The project comprised of fabrication and erection of over 1000 tons of plate work including tanks, hoppers, chutes and bag splitters.
Installation of mechanical equipment including a primary crusher, pumps and valves.