H Young & Co. (E.A.) Ltd

Provision of Installation of Bolted Tanks, Bitutainers and Interconnecting Pipework Services

Client TULLOW KENYA B.V. 7TH FLOOR, WEST END TOWERS MUTHANGARI DRIVE, OFF WAIYAKI WAY, P.O. BOX 63298-00619 NAIROBI, KENYA
Completion date MAY 2018
Project Value US$ 1,841,131.47  

Major works executed:

Ngamia-3 Site

  • Installation of 4 x 5,000 bbls site erected bolted tanks on Ngamia-3 well site.
  • Supply, installation and testing of interconnecting piping, manifold and auxiliaries, for 4 x 5000bbl

Ngamia 6 – Site

  • Installation of 4 x 5,000 bbls site erected bolted tanks on Ngamia-6 well site and interconnecting piping on site.
  • Supply, installation and testing of interconnecting piping, manifold and auxiliaries, for 4x 5000bbls tanks.

Ngamia-8 Site

  • Installation of 30 x 400 bbl bitutainers and 50 x 150bbl Iso-tanks bitutainers and interconnecting piping on site.
  • Supply, installation and testing of interconnecting piping, manifold and auxiliaries, for 50 Bitutainers
  • All Piping, valves and connections complied with applicable API/ANSI/ASME codes for crude oil and steam piping including API 12B Specification for storage of production liquids.

Applied Standards

  • Bolted tanks to API 12B
  • Feed & return lines, Control Valves and connections to PED 97/32/EC
  • Pipe to API 5L standards, Valves to API standards
  • Fittings to ASME 16.9 and 16.11standards, Flanges to ANSI B16.5 standards
  • Tracked lifting equipment for laying and installation of pipelines
  • Welding qualifications to ASME Section IX
  • Pressure vessel design and fabrications to ASME Section VIII
  • Welding using GTAW and SMAW to AWS/ANSI standards