![](https://hyoung.com/wp-content/uploads/2009/11/machakos-turnoff.jpg)
Client | MINISTRY OF ROADS & PUBLIC WORKS, KENYA |
Supervising Engineer | CHIEF ENGINEER, ROADS |
Completion date | November 2009 |
Project Value | KES 1,474,950,238 (US$ 21.019 Million) |
- Construction of Earthworks -387,000 m3.
- Cement stabilized sub-base and base -74,000 m3.
- Application of 50mm of Asphalt Concrete -17,900m3.
- Construction of pipe culverts, bridges, box culverts and other drainage works.
- Protection works using stone pitching and gabions.
- Provision of road furniture including road marking and traffic signs.
_________________
Country: Kenya
Operating Division: Road & Infrastructure Works
Market: Roads
_________________
Project Gallery
![](https://hyoung.com/wp-content/uploads/2009/11/Compaction-300x225.jpg)
![](https://hyoung.com/wp-content/uploads/2009/11/Mobile-Crusher-crushing-base-material-300x225.jpg)
![](https://hyoung.com/wp-content/uploads/2009/11/Surface-dressing-in-progress-300x225.jpg)
![](https://hyoung.com/wp-content/uploads/2009/11/DSC01665-300x225.jpg)
![](https://hyoung.com/wp-content/uploads/2009/11/Scarifying-existing-tarmac-300x225.jpg)
![](https://hyoung.com/wp-content/uploads/2009/11/Surface-dressing-300x225.jpg)