Upgrading of North Pemba Rural Roads to bitumen standard

Client CHIEF EXECUTIVE OFFICER MILLENNIUM CHALLENGE ACCOUNT – TANZANIA   Supervising Engineer LEA ASSOCIATES SOUTH ASIA PVT LTD   Completion date MARCH 2014   Project Value TZS 38,247 Million (US$ 25.48 Million)   The project consisted of upgrading of 6 rural roads located in North Pemba of Zanzibar Archipelago to bitumen standard. The total length […]

Portfolio

Ticts Container Terminal Expansion Project – Package 3 At The Port Of Dar Es Salaam

Client TANZANIA INTERNATIONAL CONTAINER SERVICES LTD (TICTS)   Supervising Engineer AMBICON ENGINEERING LTD   Commence date   MAY 2011 Completion date AUGUST 2012   Project Value US$ 6.5 MILLION   Rehabilitation of existing container terminal, installation of new crane beam and fenders Works executed under this contract comprised of the following Installation of 2 No. […]

Portfolio

Construction of Access Road to Kwale Mineral Sands Project

Client BASE TITANIUM LTD   Supervising Engineer HOWARD HUMPHREYS   Completion date AUGUST 2012   Project Value KES 482,785,725 (US$ 5.7 Million)   The access road was 7.7km consisting of a 6.5m wide main carriage way with 1m wide shoulders. It was surfaced with a 50mm layer Asphalt Concrete on the carriageway and 25mm on […]

Portfolio

Upgrading to Bitumen Standard of Kendu Bay Homa Bay Road

Client DIRECTOR GENERAL KENYA NATIONAL HIGHWAYS AUTHORITY   Supervising Engineer GENERAL MANAGER (DESIGN & CONSTRUCTION)   Completion date MARCH 2012   Project Value KES 3,359,623,063 (US$ 41.99 Million)   The Project road was approximately 38 km in length, located in Homa Bay County. It started at Kendu Bay at the shores of Lake Victoria, it also […]

Portfolio

Construction of Daraja Mbili-Nyatieko-Eronge-Kegogi-Miruka Road

Client DIRECTOR GENERAL KENYA RURAL ROADS AUTHORITY   Supervising Engineer GENERAL MANAGER (DESIGN & CONSTRUCTION)   Completion date DECEMBER 2011   Project Value KES 2,074,222,038 (US$ 30.24 Million)   The Project roads are approximately 50 km long in total and are located within the Kisii and Nyamira districts, Nyanza province primarily involved construction of a […]

Portfolio

Upgrading of Kipevu Oil Storage Facility Motor Spirit Premium and Dual Purpose Kerosene Pipework

Client KENYA PIPELINE COMPANY   Supervising Engineer KPC ENGINEERING MANAGER   Commencement date   JANUARY 2011 Completion date DECEMBER 2011   Project Value KES 321 MILLION (US$ 3.78 MILLION)   Kenya Pipeline Company – Rehabilitation of Tanks and Pipelines Rehabilitation of Petroleum Storage Tanks at Mombasa, Nairobi, Nakuru, Eldoret and Kisumu terminals. Details Upgrading of […]

Portfolio

Construction of Meru-Mikinduri-Maua Road

Client MINISTRY OF ROADS & PUBLIC WORKS, KENYA/ DIRECTOR GENERAL KENYA RURAL ROADS AUTHORITY   Supervising Engineer CHIEF ENGINEER, ROADS   Completion date September 2010   Project Value KES 1,918,694,062.48 (US$ 28.42 Million)   The Project road is 52 km long and covers three districts, namely North Imenti, Tigania and Igembe in Meru County and […]

Portfolio

Rehabilitation of Enterprise & Lusaka Roads, Nairobi

Client TOWN CLERK, CITY COUNCIL OF NAIROBI   Supervising Engineer CITY ENGINEER, CITY COUNCIL OF NAIROBI   Completion date JUNE 2010   Project Value KES 857,129,926 (US$ 10.965 Million)   The Project consisted of the rehabilitation of the main arteries into Industrial Area, Nairobi with Enterprise Road running from Mombasa Road to Factory Street, while […]

Portfolio

Olkaria II Unit 3 Geothermal Power Project

Client MITSUBISHI HEAVY INDUSTRIES/ MITSUBISHI CORPORATION CONSORTIUM FOR KENYA ELECTRICITY GENERATING CO. (KENGEN)   Supervising Engineer SINCLAR KNIGHT MERZ (NOW PART OF JACOBS ENGINEERING)   Commence date   FEBRUARY 2008 Completion date MAY 2010   Project Value US$ 36.5 Million   Installation of additional geothermal turbine generating unit with a Normal Continuous Rating (NCR) of […]

Portfolio

Repair & Rehabilitation of Machakos Turnoff – Masii (C97) Road

Client MINISTRY OF ROADS & PUBLIC WORKS, KENYA   Supervising Engineer CHIEF ENGINEER, ROADS   Completion date November 2009   Project Value KES 1,474,950,238  (US$ 21.019 Million)   The Machakos Turnoff – Masii lies to the southeast of Nairobi. This project was divided into four sections and had a total project length 78 km. Section […]